Zeiss Norditalien, Oberkochen
Zeiss Norditalien, Bergamo + Mailand
Carl-Zeiss-Straße, 73447 Oberkochen
Construction year2024
Project descriptionAnother expansion of the large Zeiss campus in Oberkochen was realized under the project name Zeiss North-Italy. As with the previously constructed production halls for semiconductor products, massive 1.50 m thick floor slabs were designed here as well, executed as jointless structures. The implementation followed the same approach as with the earlier foundation slabs, using combined reinforcement to consistently apply the efficient construction method to these new sections as well.
- Constructability and time savings -> Starting production as early as possible was top priority
- Vibration-resistant, monolithic foundation slabs without construction joints
- Reduction of execution time was a dominant factor for feasibility
- Simplified reinforcement layout
- Building on the former successful way of execution with combined reinforcement
150 cm
Executioncombined reinforcement
ConcreteC25/30
Performance classL1,8/1,8
Fibre typeDramix® 4D 65/60BG
Carl-Zeiss AG, 73447 Oberkochen
General contractorGLASS GmbH BAUUNTERNEHMUNG
Original solutionaitp GmbH, 09111 Chemnitz
back to the list of projects: